Skip to content

Project Phases & Milestones

Progress is tracked across the phases of a project — for example DBM, FEED, Detailing, Procurement, Construction, Pre-Commissioning, Commissioning, and Handover.

Each phase defines its own set of milestones, and the milestones within a phase sum to 100%. Each milestone is linked to a cost code. The progressing template for a tag stays the same, while the milestones differ per phase — so the same tag can be progressed consistently through engineering, construction, commissioning, and handover.

Key points

  • A tag’s progress is monitored separately at each project phase.
  • Milestones map to cost codes for earned-value reporting.
  • The same cost code may be reused across milestones within a phase.

Note

This area is under active development (milestone-level vs template-level phase handling). Confirm the final screens and add screenshots.